We are approaching some important milestones in the renovation of The 411.

 

The coping installation will start soon, which will complete the building envelope. Work is underway on the exterior of the building, including at the loading dock on the east side of the building and concrete work on the north side. Inside, carpet and flooring are being installed, acoustical K-13 spray is in progress and will finish this week. Drywall will also finish up this week, and walls are already being painted and light fixtures installed.

 

Our next major milestone is bringing power to the building. ComEd has installed our new transformer to the building and anticipate energizing the new service sometime in the next two weeks. Later this month, Pepper Energy will start mobilizing in preparation for the installation of the solar panels in October.


 
 
 