Flooring, Finishes and Furniture!

Oct 16
1 min read

October 16, 2026


The renovation of The 411 continues to make great progress

 

Final touches are getting started - flooring is about 70% complete and finishes and furniture going in!

 

Permanent power was solidified late last month, allowing us to turn on power for light fixtures, receptacles, mechanical equipment and more. Site lighting has started around our campus, and the solar team has installed their roof safety equipment to prepare for their infrastructure work.

 

The first loads of furniture and millwork arrived in early October. The team has started installing audio/visual this week, with TVs arriving and the team pulling cable to locations throughout the building. The demountable glass on the west half of the building for offices, conference rooms and focus rooms has been installed and installation has begun on the east half.

 

Coming up in November, wireless access points will get up and running and we will start punch list items, starting on the west half of the building. 