Gaining momentum at The 411

  • Jul 8
  • 1 min read

April 13, 2026


Construction is in full swing!


All subcontracts have been awarded, submittals and shop drawings are coming in, and we have doubled the trade power on site. Underground electrical got started last week and we will have our first inspection later this week – an important milestone for any project.


Installation of the geothermal well is starting on the north side of the building, just east of the main entrance. The geothermal well we are installing is a 400+ foot well that taps into the earth’s constant subsurface temperature to provide highly efficient heating and cooling. Ours is one of the first geothermal wells in Illinois to use a Darcy System.



 
 
 